East Side Update: Asphalt Down + Stripes Today

The asphalt on the East parking lot has been laid down, steam rolled, and ready for stripes and parking blocks.

To be completed on May 6:

  • Striping East lot parking spaces

  • Adding handicap sign poles to East spaces

  • Add parking blocks to all newly constructed spaces.

  • Add divider stripes to Lewis drive exit, East entrance, and West entrance

Work to be finished:

  • Pour sidewalks

  • Install railing on retaining wall.

  • Install light poles.

  • Grade out soil to plant seeds

  • Build a garbage dumpster enclosure on West side.

Previous
Previous

Sidewalks are completed

Next
Next

Rain Delayed One More Week