East Side Update: Asphalt Down + Stripes Today
The asphalt on the East parking lot has been laid down, steam rolled, and ready for stripes and parking blocks.
To be completed on May 6:
Striping East lot parking spaces
Adding handicap sign poles to East spaces
Add parking blocks to all newly constructed spaces.
Add divider stripes to Lewis drive exit, East entrance, and West entrance
Work to be finished:
Pour sidewalks
Install railing on retaining wall.
Install light poles.
Grade out soil to plant seeds
Build a garbage dumpster enclosure on West side.